MODULE 7: PSYCHOSOCIAL ISSUES AND OTHER MISCELLANEOUS
TOPICS IN OCCUPATIONAL AND ENVIRONMENTAL HEALTH SECTION 7: SHIFTWORK AND HOURS OF WORK: 2: Designing Shiftwork Schedules |
The most useful strategies are summarised in the box below (ILO Encyclopaedia, 1998):
This is not the physiologically preferred system. Although when at work continuously, there may be some adaptation of the body clocks, this reverts once the worker is off work and tends to follow a day/night cycle in their social lives.
More rapidly rotating schedules are more advantageous compared to weekly shift rotation. This is because a fast rotation maintains the daytime orientation of the circadian rhythm. This also prevents a chronic sleep deprivation which may arise from consecutive night shifts. It is advisable to keep night shifts to between 2 – 4 days before at least two days off. Although some workers may prefer the long stint of nightshift followed by long weekends (3-4 days off), this could lead to sleep deprivation and fatigue.
Shifts should not be longer than 12 hours, although 8 is preferrable. For shifts longer than 8 hours, the work intensity should be modified to ensure that it is lighter work. Nightshifts should be preferably of a shorter duration, with only a minimum number of 12 hour shifts.
The timing of shifts must also be considered. Starting of a morning shift too early, causes fatigue of workers who may have had a reduced number of hours of sleep. However, a later start to the early shift implies a later finish to the night shift, which may be problematic, both physiologically as well as socially (consider problems with transport, for example).
A shift system which first moves from morning shift to evening shift, and then to night shift, has a forward rotation (phase delay, clockwise rotation). An anticlockwise, or backward, rotation has a phase advance which moves from night to evening to morning shifts. The forward rotation is thought to be physiologically preferrable. A continuous shift system that has a rapid forward rotation pattern, with 8 hours of work per shift, some free weekends, at least two successive full days off and no quick changeovers, appears to be the system to be recommended. The illustration from the ILO, shown below, provides an approach to shift rotation.
Average weekly working hours: | |
---|---|
33.6 h/week | without additional rotation |
35.2 h/week | with 2 additional shifts/10 weeks |
36.8 h/week | with 4 additional shifts/10 weeks |
38.4 h/week | with 6 additional shifts/10 weeks |
40.0 h/week | with 8 additional shifts/10 weeks |
(Data extracted from the ILO Encyclopaedia, 1998) |